Leaves on the Line

Moorthorpe

MRP North & East route
CSV JSON

1,085 delay minutes

The biggest share (20%) of the delay picked up at Moorthorpe in the four weeks to 9 December 2023 came from weather and structures.

73% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track868%8% 3 a day, the most in 5 years-
Signals, points and power838%16% 3 a day, more than 1 of the other 4 years-
Weather and structures21720%7% 8 a day, the most in 5 years1
Autumn11811%7% 4 a day, the most in 5 years-
External757%4% 3 a day, the most in 5 years-
Network management16015%17% 6 a day, more than 3 of the other 4 years4
The operators' causes
Train faults11611%16% 4 a day, more than 1 of the other 4 years-
Traincrew10410%11% 4 a day, the most in 5 years4
Stations303%3% 1 a day, more than 1 of the other 4 years-
Operations434%5% 2 a day, more than 2 of the other 4 years-
Operator, other555%7% 2 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail180
TGDriver82
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.78
QJSpecial working for leaf-fall track circuit operation64
XPBRIDGE HIT55
OUDelays not Investigated by Network Rail39
Q3NZ Pumps T34
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)31
M8Technical failures above the Solebar28
IBPoints failure (including no fault found)25
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar1,783
TGDriver1,726
RCre-booked assistance for a person with reduced mobility joining/alighting,1,636
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,492
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps1,184
XPBRIDGE HIT1,166
IBPoints failure (including no fault found)971
RBPassengers joining/alighting853
ICTrack circuit failure (including no fault found)841
M8Technical failures above the Solebar808