Maryport
103 delay minutes
Most of the delay picked up at Maryport in the four weeks to 9 December 2023 came from weather and structures.
92% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 14 | 14% | 16% | - |
| Weather and structures | 73 | 71% | 7% | 4 |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 16 | 16% | 17% | 4 |
| The operators' causes | ||||
| Train faults | - | - | 16% | 1 |
| Traincrew | - | - | 11% | 3 |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | 1 |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 73 |
| I5 | Possession over-run from planned work | 15 |
| IC | Track circuit failure (including no fault found) | 14 |
| ZY | Univestigated station overtime System Roll-up Only | 1 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OL | Signal Box not open during booked hours | 126 |
| IC | Track circuit failure (including no fault found) | 89 |
| IB | Points failure (including no fault found) | 80 |
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 73 |
| JK | Flooding not due to exceptional weather | 71 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 70 |
| MD | Technical failures below the solebar | 49 |
| TG | Driver | 49 |
| IA | Signal failure (including no fault found) | 41 |
| I5 | Possession over-run from planned work | 33 |