Leaves on the Line

Marsden

MSN North & East route
CSV JSON

1,424 delay minutes

The biggest share (22%) of the delay picked up at Marsden in the four weeks to 9 December 2023 came from track faults.

57% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track31522%8% 11 a day, the most in 5 years-
Signals, points and power15811%16% 6 a day, the most in 5 years-
Weather and structures1198%7% 4 a day, the most in 5 years-
Autumn483%7% 2 a day, more than 1 of the other 4 years-
External302%4% 1 a day, the most in 5 years-
Network management30021%17% 11 a day, more than 3 of the other 4 years12
The operators' causes
Train faults13710%16% 5 a day, more than 3 of the other 4 years-
Traincrew17112%11% 6 a day, more than 2 of the other 4 years1
Stations363%3% 1 a day, more than 3 of the other 4 years-
Operations775%5% 3 a day, the most in 5 years-
Operator, other342%7% 1 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IRBroken/cracked/twisted/buckled/flawed rail289
TGDriver135
OUDelays not Investigated by Network Rail121
J3Axle Counter Failure97
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)56
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions43
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)42
MDTechnical failures below the solebar41
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)38
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail35
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver4,295
MDTechnical failures below the solebar2,330
ZUNo Cause Identified After investigation by both Parties1,451
TH(Senior) Conductor/Train Manager1,420
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,376
M7Door and Door system faults1,360
M8Technical failures above the Solebar1,316
Q1Takeback Pumps1,209
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,083
MUDepot operating problem948