Leaves on the Line

Mountain Ash

MTA Cardiff Valleys route
CSV JSON

145 delay minutes

The biggest share (22%) of the delay picked up at Mountain Ash in the four weeks to 9 December 2023 came from signal, points and power faults.

90% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1812%8% 1 a day, the most in 5 years-
Signals, points and power3222%16% 1 a day, more than 3 of the other 4 years-
Weather and structures86%7% 0 a day, more than 3 of the other 4 years-
Autumn--7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management1410%17% 1 a day, more than 1 of the other 4 years-
The operators' causes
Train faults2618%16% 1 a day, more than 1 of the other 4 years2
Traincrew1510%11% 1 a day, more than 2 of the other 4 years-
Stations1712%3% 1 a day, more than 2 of the other 4 years-
Operations1510%5% 1 a day, more than 1 of the other 4 years1
Operator, other--7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
J3Axle Counter Failure23
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps16
TZOther Passenger Train Operating Company causes15
OCSignaller including mis-routing (not ERTM /ETCS related)14
JATSR speed restrictions for track work outside of the Timetable Planning Rules12
T2Delay at unstaffed station to non-DOO train10
IBPoints failure (including no fault found)9
T3Waiting connections from other transport modes8
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure8
RQUn-booked assistance for a person with reduced mobility joining/alighting,7
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)1,041
OUDelays not Investigated by Network Rail410
J3Axle Counter Failure390
TGDriver385
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)344
MDTechnical failures below the solebar336
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps330
M8Technical failures above the Solebar300
T2Delay at unstaffed station to non-DOO train296
M7Door and Door system faults294