Newbury
3,710 delay minutes
The biggest share (22%) of the delay picked up at Newbury in the four weeks to 9 December 2023 came from faulty trains.
73% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 522 | 14% | 8% | 19 a day, the most in 5 years | 3 |
| Signals, points and power | 571 | 15% | 16% | 20 a day, more than 1 of the other 4 years | 3 |
| Weather and structures | 89 | 2% | 7% | 3 a day, more than 2 of the other 4 years | - |
| Autumn | 238 | 6% | 7% | 8 a day, the most in 5 years | - |
| External | 183 | 5% | 4% | 7 a day, more than 3 of the other 4 years | 1 |
| Network management | 533 | 14% | 17% | 19 a day, the most in 5 years | 50 |
| The operators' causes | |||||
| Train faults | 813 | 22% | 16% | 29 a day, more than 3 of the other 4 years | 11 |
| Traincrew | 421 | 11% | 11% | 15 a day, the most in 5 years | 2 |
| Stations | 14 | <1% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 43 | 1% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 284 | 8% | 7% | 10 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 414 |
| IB | Points failure (including no fault found) | 325 |
| MC | Diesel Loco failure, defect, attention | 299 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 278 |
| Q3 | NZ Pumps T | 212 |
| TT | Leaf fall Neutral | 212 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 193 |
| OU | Delays not Investigated by Network Rail | 187 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 137 |
| M7 | Door and Door system faults | 117 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 7,674 |
| TG | Driver | 6,760 |
| MD | Technical failures below the solebar | 6,184 |
| J3 | Axle Counter Failure | 5,772 |
| IC | Track circuit failure (including no fault found) | 5,420 |
| ZU | No Cause Identified After investigation by both Parties | 5,345 |
| IB | Points failure (including no fault found) | 5,240 |
| JH | Critical Rail Temperature speeds, (other than buckled rails) | 3,114 |
| IA | Signal failure (including no fault found) | 3,102 |
| M8 | Technical failures above the Solebar | 3,101 |