North Fambridge
59 delay minutes
Most of the delay picked up at North Fambridge in the four weeks to 9 December 2023 came from faulty trains.
76% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 4 | 7% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | - | - | 16% | 0 a day, the least in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 11 | 18% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 3 | 5% | 17% | 0 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 30 | 51% | 16% | 1 a day, more than 3 of the other 4 years | - |
| Traincrew | 1 | 2% | 11% | 0 a day, the least in 5 years | - |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 11 | 18% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M8 | Technical failures above the Solebar | 22 |
| Q3 | NZ Pumps T | 11 |
| TT | Leaf fall Neutral | 9 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 8 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4 |
| QM | Train schedule/STP Process including erroneous simplifiers | 3 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 2 |
| TG | Driver | 1 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 11,047 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,125 |
| TG | Driver | 495 |
| MD | Technical failures below the solebar | 493 |
| XP | BRIDGE HIT | 419 |
| IC | Track circuit failure (including no fault found) | 363 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 362 |
| M8 | Technical failures above the Solebar | 287 |
| II | Signalling lineside cable fault | 277 |
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 261 |