Leaves on the Line

Nailsea & Backwell

NLS Western route
CSV JSON

597 delay minutes

The biggest share (23%) of the delay picked up at Nailsea & Backwell in the four weeks to 9 December 2023 came from how the network was run.

50% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track376%8% 1 a day, the most in 5 years-
Signals, points and power336%16% 1 a day, more than 2 of the other 4 years-
Weather and structures468%7% 2 a day, the most in 5 years-
Autumn6912%7% 2 a day, the most in 5 years-
External427%4% 2 a day, the most in 5 years-
Network management13723%17% 5 a day, the most in 5 years-
The operators' causes
Train faults7613%16% 3 a day, the most in 5 years-
Traincrew7613%11% 3 a day, the most in 5 years-
Stations2<1%3% 0 a day, the least in 5 years-
Operations153%5% 1 a day, more than 3 of the other 4 years-
Operator, other6411%7% 2 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver67
Q3NZ Pumps T64
TTLeaf fall Neutral64
OCSignaller including mis-routing (not ERTM /ETCS related)61
XBVandalism or theft (including the placing of objects on the line)35
MDTechnical failures below the solebar34
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.31
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure22
JKFlooding not due to exceptional weather21
OUDelays not Investigated by Network Rail16
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver1,611
MDTechnical failures below the solebar1,442
ZUNo Cause Identified After investigation by both Parties1,174
J3Axle Counter Failure1,141
M7Door and Door system faults748
M8Technical failures above the Solebar676
OCSignaller including mis-routing (not ERTM /ETCS related)668
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps663
Q3NZ Pumps T604
ICTrack circuit failure (including no fault found)593