824 delay minutes
The biggest share (32%) of the delay picked up at New Mills Central in the four weeks to 9 December 2023 came from autumn leaves.
65% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 113 | 14% | 8% | 4 a day, the most in 5 years | - |
| Signals, points and power | 45 | 5% | 16% | 2 a day, more than 1 of the other 4 years | 1 |
| Weather and structures | 16 | 2% | 7% | 1 a day, more than 1 of the other 4 years | - |
| Autumn | 266 | 32% | 7% | 9 a day, the most in 5 years | - |
| External | 17 | 2% | 4% | 1 a day, more than 3 of the other 4 years | - |
| Network management | 158 | 19% | 17% | 6 a day, the most in 5 years | 4 |
| The operators' causes | |||||
| Train faults | 75 | 9% | 16% | 3 a day, more than 2 of the other 4 years | 1 |
| Traincrew | 83 | 10% | 11% | 3 a day, more than 2 of the other 4 years | 5 |
| Stations | 9 | 1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 16 | 2% | 5% | 1 a day, the least in 5 years | - |
| Operator, other | 27 | 3% | 7% | 1 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 233 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 92 |
| OU | Delays not Investigated by Network Rail | 68 |
| TG | Driver | 65 |
| J5 | Infrastructure Asset fault reported but proven to be mistaken | 36 |
| IB | Points failure (including no fault found) | 30 |
| M9 | Reported fleet equipment defect - no fault found | 28 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 23 |
| QI | Cautioning due to railhead leaf contamination | 23 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 22 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 2,197 |
| MD | Technical failures below the solebar | 1,996 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,535 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 1,229 |
| IB | Points failure (including no fault found) | 868 |
| M8 | Technical failures above the Solebar | 808 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 781 |
| MC | Diesel Loco failure, defect, attention | 738 |
| M7 | Door and Door system faults | 705 |
| IC | Track circuit failure (including no fault found) | 679 |