Nunthorpe
1,434 delay minutes
The biggest share (20%) of the delay picked up at Nunthorpe in the four weeks to 9 December 2023 came from how the network was run.
81% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 39 | 3% | 8% | 1 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 126 | 9% | 16% | 5 a day, more than 3 of the other 4 years | - |
| Weather and structures | 84 | 6% | 7% | 3 a day, the most in 5 years | - |
| Autumn | 81 | 6% | 7% | 3 a day, the most in 5 years | - |
| External | 70 | 5% | 4% | 3 a day, more than 3 of the other 4 years | - |
| Network management | 291 | 20% | 17% | 10 a day, more than 3 of the other 4 years | 3 |
| The operators' causes | |||||
| Train faults | 223 | 16% | 16% | 8 a day, the most in 5 years | - |
| Traincrew | 153 | 11% | 11% | 5 a day, the most in 5 years | 5 |
| Stations | 99 | 7% | 3% | 4 a day, the most in 5 years | - |
| Operations | 230 | 16% | 5% | 8 a day, the most in 5 years | 1 |
| Operator, other | 38 | 3% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TZ | Other Passenger Train Operating Company causes | 155 |
| OU | Delays not Investigated by Network Rail | 144 |
| M7 | Door and Door system faults | 105 |
| TG | Driver | 86 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 79 |
| TH | (Senior) Conductor/Train Manager | 63 |
| J0 | Telecom equipment radio failure (GSM-R) | 62 |
| MD | Technical failures below the solebar | 51 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 51 |
| XP | BRIDGE HIT | 50 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 6,296 |
| TG | Driver | 2,490 |
| TZ | Other Passenger Train Operating Company causes | 2,360 |
| MD | Technical failures below the solebar | 1,794 |
| RB | Passengers joining/alighting | 1,731 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,417 |
| JH | Critical Rail Temperature speeds, (other than buckled rails) | 1,374 |
| IB | Points failure (including no fault found) | 1,333 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 1,060 |
| M7 | Door and Door system faults | 975 |