Leaves on the Line

Newquay

NQY Western route
CSV JSON

155 delay minutes

The biggest share (35%) of the delay picked up at Newquay in the four weeks to 9 December 2023 came from signal, points and power faults.

64% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track85%8%-
Signals, points and power5435%16%2
Weather and structures2617%7%-
Autumn--7%-
External117%4%-
Network management2114%17%1
The operators' causes
Train faults3221%16%1
Traincrew--11%3
Stations32%3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles45
M0Confirmed train cab based safety system fault (including GSMR)32
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure16
OUDelays not Investigated by Network Rail11
XBVandalism or theft (including the placing of objects on the line)11
JKFlooding not due to exceptional weather10
IRBroken/cracked/twisted/buckled/flawed rail6
ICTrack circuit failure (including no fault found)5
IASignal failure (including no fault found)4
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)4
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar790
TGDriver388
IBPoints failure (including no fault found)335
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles300
ICTrack circuit failure (including no fault found)189
ZUNo Cause Identified After investigation by both Parties185
M8Technical failures above the Solebar182
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.176
M7Door and Door system faults175
J3Axle Counter Failure137