1,519 delay minutes

The biggest share (19%) of the delay picked up at Norwich in the four weeks to 9 December 2023 came from faulty trains.

81% of these minutes were knock-on from something that happened elsewhere first. 88% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1087%8% 4 a day, more than 2 of the other 4 years5
Signals, points and power22115%16% 8 a day, more than 2 of the other 4 years5
Weather and structures594%7% 2 a day, more than 3 of the other 4 years-
Autumn22215%7% 8 a day, the most in 5 years-
External1178%4% 4 a day, more than 3 of the other 4 years-
Network management22715%17% 8 a day, more than 3 of the other 4 years8
The operators' causes
Train faults28219%16% 10 a day, more than 1 of the other 4 years2
Traincrew1339%11% 5 a day, more than 3 of the other 4 years2
Stations6<1%3% 0 a day, more than 2 of the other 4 years-
Operations312%5% 1 a day, more than 3 of the other 4 years-
Operator, other1147%7% 4 a day, more than 2 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
QJSpecial working for leaf-fall track circuit operation173
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure124
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.98
XPBRIDGE HIT72
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards64
M8Technical failures above the Solebar58
V8Train striking or being struck by a bird52
MDTechnical failures below the solebar47
M7Door and Door system faults45
I8Animal Strike or Incursion within the control of Network Rail44
Since 2018
CodeWhat Network Rail loggedMinutes
MUDepot operating problem8,394
MDTechnical failures below the solebar6,782
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.6,620
M8Technical failures above the Solebar5,794
TGDriver4,444
Q1Takeback Pumps4,030
JSCondition of Track TSR outside the Timetable Planning Rules3,768
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure3,703
M7Door and Door system faults3,563
DDTechnical Fleet Holding Code3,042