Ockendon
90 delay minutes
The biggest share (38%) of the delay picked up at Ockendon in the four weeks to 9 December 2023 came from traincrew problems.
64% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 2 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 8 | 9% | 16% | 0 a day, more than 1 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 18 | 19% | 17% | 1 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 14 | 16% | 16% | 1 a day, more than 3 of the other 4 years | - |
| Traincrew | 34 | 38% | 11% | 1 a day, more than 3 of the other 4 years | 1 |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | 5 | 5% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 10 | 11% | 7% | 0 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TW | Driver adhering to company professional driving standards or policy | 16 |
| M8 | Technical failures above the Solebar | 14 |
| TG | Driver | 14 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 10 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 7 |
| J0 | Telecom equipment radio failure (GSM-R) | 5 |
| FC | Freight Train Driver error, SPAD, Wrong routing or Missed AWS/DSD [No change] | 4 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 4 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 4 |
| IH | Power Supply And Distribution System Failure | 3 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IR | Broken/cracked/twisted/buckled/flawed rail | 929 |
| TG | Driver | 418 |
| TW | Driver adhering to company professional driving standards or policy | 271 |
| QM | Train schedule/STP Process including erroneous simplifiers | 270 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 264 |
| IC | Track circuit failure (including no fault found) | 250 |
| XR | Cable vandalism or theft | 243 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 232 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 232 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 224 |