Oulton Broad South
12 delay minutes
Most of the delay picked up at Oulton Broad South in the four weeks to 9 December 2023 came from track faults.
100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | 12 | 100% | 8% | 1 |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | - | - | 17% | - |
| The operators' causes | ||||
| Train faults | - | - | 16% | - |
| Traincrew | - | - | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 12 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 78 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 72 |
| JF | Off track asset defects or issues on the NR network (not due to vandalism or weather or part of station infrastructure) | 59 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 26 |
| J3 | Axle Counter Failure | 13 |
| M7 | Door and Door system faults | 13 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 11 |
| M8 | Technical failures above the Solebar | 10 |
| MD | Technical failures below the solebar | 8 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 8 |