Leaves on the Line

Pontefract Monkhill

PFM North & East route
CSV JSON

752 delay minutes

The biggest share (22%) of the delay picked up at Pontefract Monkhill in the four weeks to 9 December 2023 came from how the network was run.

60% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track385%8% 1 a day, more than 3 of the other 4 years-
Signals, points and power345%16% 1 a day, more than 3 of the other 4 years1
Weather and structures7710%7% 3 a day, more than 3 of the other 4 years-
Autumn11115%7% 4 a day, more than 3 of the other 4 years-
External324%4% 1 a day, the most in 5 years-
Network management16522%17% 6 a day, more than 3 of the other 4 years1
The operators' causes
Train faults12717%16% 5 a day, more than 2 of the other 4 years2
Traincrew314%11% 1 a day, more than 1 of the other 4 years1
Stations253%3% 1 a day, more than 2 of the other 4 years-
Operations182%5% 1 a day, more than 2 of the other 4 years-
Operator, other9513%7% 3 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T92
TTLeaf fall Neutral92
OUDelays not Investigated by Network Rail68
OCSignaller including mis-routing (not ERTM /ETCS related)56
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail47
MTConfirmed train borne safety system faults (not cab based)35
MNBrake and brake systems faults; including wheel flats where no other cause had been identified26
MDTechnical failures below the solebar25
JKFlooding not due to exceptional weather23
M8Technical failures above the Solebar23
Since 2018
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,584
MDTechnical failures below the solebar1,375
TGDriver1,278
IBPoints failure (including no fault found)1,159
RCre-booked assistance for a person with reduced mobility joining/alighting,1,079
Q3NZ Pumps T803
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps788
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.782
M7Door and Door system faults677
ICTrack circuit failure (including no fault found)675