Paignton
177 delay minutes
The biggest share (38%) of the delay picked up at Paignton in the four weeks to 9 December 2023 came from signal, points and power faults.
77% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 3 | 2% | 8% | 0 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 67 | 38% | 16% | 2 a day, more than 3 of the other 4 years | 3 |
| Weather and structures | 10 | 6% | 7% | 0 a day, more than 1 of the other 4 years | 5 |
| Autumn | 3 | 1% | 7% | 0 a day, the least in 5 years | - |
| External | 17 | 10% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 29 | 16% | 17% | 1 a day, more than 1 of the other 4 years | 115 |
| The operators' causes | |||||
| Train faults | 26 | 15% | 16% | 1 a day, more than 1 of the other 4 years | 2 |
| Traincrew | 3 | 2% | 11% | 0 a day, the least in 5 years | 9 |
| Stations | 7 | 4% | 3% | 0 a day, the least in 5 years | - |
| Operations | 7 | 4% | 5% | 0 a day, the most in 5 years | 1 |
| Operator, other | 6 | 3% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| J3 | Axle Counter Failure | 45 |
| IC | Track circuit failure (including no fault found) | 20 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 17 |
| OU | Delays not Investigated by Network Rail | 16 |
| M8 | Technical failures above the Solebar | 15 |
| JK | Flooding not due to exceptional weather | 8 |
| TZ | Other Passenger Train Operating Company causes | 7 |
| ZY | Univestigated station overtime System Roll-up Only | 6 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 5 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 4 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 1,893 |
| IC | Track circuit failure (including no fault found) | 1,495 |
| M7 | Door and Door system faults | 1,211 |
| TG | Driver | 1,062 |
| IB | Points failure (including no fault found) | 801 |
| M8 | Technical failures above the Solebar | 716 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 617 |
| ZU | No Cause Identified After investigation by both Parties | 570 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 523 |
| ZY | Univestigated station overtime System Roll-up Only | 517 |