Penzance
956 delay minutes
The biggest share (22%) of the delay picked up at Penzance in the four weeks to 9 December 2023 came from track faults.
75% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 215 | 22% | 8% | 8 a day, the most in 5 years | 3 |
| Signals, points and power | 181 | 19% | 16% | 6 a day, more than 2 of the other 4 years | - |
| Weather and structures | 76 | 8% | 7% | 3 a day, more than 2 of the other 4 years | 3 |
| Autumn | 34 | 4% | 7% | 1 a day, more than 1 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 155 | 16% | 17% | 6 a day, the most in 5 years | 26 |
| The operators' causes | |||||
| Train faults | 71 | 7% | 16% | 3 a day, more than 2 of the other 4 years | 3 |
| Traincrew | 158 | 17% | 11% | 6 a day, the most in 5 years | 18 |
| Stations | 10 | 1% | 3% | 0 a day, more than 3 of the other 4 years | - |
| Operations | 30 | 3% | 5% | 1 a day, the most in 5 years | 1 |
| Operator, other | 26 | 3% | 7% | 1 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 149 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 137 |
| IC | Track circuit failure (including no fault found) | 92 |
| OU | Delays not Investigated by Network Rail | 92 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 78 |
| J3 | Axle Counter Failure | 42 |
| JK | Flooding not due to exceptional weather | 42 |
| MU | Depot operating problem | 40 |
| I5 | Possession over-run from planned work | 33 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 31 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,228 |
| MD | Technical failures below the solebar | 4,384 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 2,426 |
| M8 | Technical failures above the Solebar | 2,175 |
| IB | Points failure (including no fault found) | 2,171 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,002 |
| M7 | Door and Door system faults | 1,625 |
| IA | Signal failure (including no fault found) | 1,624 |
| MU | Depot operating problem | 1,598 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,434 |