Leaves on the Line

Putney

PUT Wessex route
CSV JSON

147 delay minutes

The biggest share (22%) of the delay picked up at Putney in the four weeks to 9 December 2023 came from faulty trains.

55% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power2014%16% 1 a day, more than 1 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn21%7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management3121%17% 1 a day, the least in 5 years-
The operators' causes
Train faults3222%16% 1 a day, more than 1 of the other 4 years-
Traincrew107%11% 0 a day, more than 1 of the other 4 years-
Stations2718%3% 1 a day, the most in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other2517%7% 1 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
M7Door and Door system faults25
VHPassenger Communication cord, door egress or emergency train alarm operated21
ICTrack circuit failure (including no fault found)14
I6Delays as a result of line blocks / track patrols (including late handback)10
RYMishap - Station Operating causes8
T2Delay at unstaffed station to non-DOO train8
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)8
MDTechnical failures below the solebar7
TGDriver7
OCSignaller including mis-routing (not ERTM /ETCS related)6
Since 2018
CodeWhat Network Rail loggedMinutes
I6Delays as a result of line blocks / track patrols (including late handback)1,853
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,307
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)917
VHPassenger Communication cord, door egress or emergency train alarm operated898
TGDriver882
ICTrack circuit failure (including no fault found)805
IBPoints failure (including no fault found)548
M7Door and Door system faults491
MDTechnical failures below the solebar453
I9Fires starting on Network Rail Infrastructure433