Leaves on the Line

Redbridge (Hants)

RDB Wessex route
CSV JSON

1,387 delay minutes

The biggest share (25%) of the delay picked up at Redbridge (Hants) in the four weeks to 9 December 2023 came from signal, points and power faults.

81% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1098%8% 4 a day, more than 2 of the other 4 years-
Signals, points and power35125%16% 13 a day, the most in 5 years-
Weather and structures232%7% 1 a day, more than 1 of the other 4 years-
Autumn1047%7% 4 a day, the most in 5 years-
External201%4% 1 a day, more than 2 of the other 4 years-
Network management24718%17% 9 a day, more than 3 of the other 4 years-
The operators' causes
Train faults32023%16% 11 a day, the most in 5 years-
Traincrew363%11% 1 a day, the least in 5 years-
Stations222%3% 1 a day, more than 2 of the other 4 years-
Operations624%5% 2 a day, the most in 5 years-
Operator, other937%7% 3 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar243
IESignalling Functional Power Supply Failure158
IBPoints failure (including no fault found)92
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.90
OMTechnical failure associated with a Railhead conditioning train88
Q3NZ Pumps T66
TTLeaf fall Neutral66
TBTrain cancelled or delayed at Train Operators request42
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)40
IISignalling lineside cable fault30
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.25,994
ICTrack circuit failure (including no fault found)7,597
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,280
MDTechnical failures below the solebar1,980
TGDriver1,852
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,666
IBPoints failure (including no fault found)1,435
OCSignaller including mis-routing (not ERTM /ETCS related)1,317
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)1,278
IHPower Supply And Distribution System Failure1,105