Redbridge (Hants)
1,387 delay minutes
The biggest share (25%) of the delay picked up at Redbridge (Hants) in the four weeks to 9 December 2023 came from signal, points and power faults.
81% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 109 | 8% | 8% | 4 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 351 | 25% | 16% | 13 a day, the most in 5 years | - |
| Weather and structures | 23 | 2% | 7% | 1 a day, more than 1 of the other 4 years | - |
| Autumn | 104 | 7% | 7% | 4 a day, the most in 5 years | - |
| External | 20 | 1% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 247 | 18% | 17% | 9 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 320 | 23% | 16% | 11 a day, the most in 5 years | - |
| Traincrew | 36 | 3% | 11% | 1 a day, the least in 5 years | - |
| Stations | 22 | 2% | 3% | 1 a day, more than 2 of the other 4 years | - |
| Operations | 62 | 4% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 93 | 7% | 7% | 3 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 243 |
| IE | Signalling Functional Power Supply Failure | 158 |
| IB | Points failure (including no fault found) | 92 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 90 |
| OM | Technical failure associated with a Railhead conditioning train | 88 |
| Q3 | NZ Pumps T | 66 |
| TT | Leaf fall Neutral | 66 |
| TB | Train cancelled or delayed at Train Operators request | 42 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 40 |
| II | Signalling lineside cable fault | 30 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 25,994 |
| IC | Track circuit failure (including no fault found) | 7,597 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2,280 |
| MD | Technical failures below the solebar | 1,980 |
| TG | Driver | 1,852 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,666 |
| IB | Points failure (including no fault found) | 1,435 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,317 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 1,278 |
| IH | Power Supply And Distribution System Failure | 1,105 |