Leaves on the Line

Rock Ferry

RFY North West route
CSV JSON

763 delay minutes

The biggest share (43%) of the delay picked up at Rock Ferry in the four weeks to 9 December 2023 came from faulty trains.

57% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power324%16% 1 a day, the least in 5 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn8311%7% 3 a day, the most in 5 years-
External20226%4% 7 a day, the most in 5 years2
Network management426%17% 2 a day, the least in 5 years24
The operators' causes
Train faults32843%16% 12 a day, the most in 5 years16
Traincrew588%11% 2 a day, more than 3 of the other 4 years-
Stations--3% 0 a day, the least in 5 years-
Operations162%5% 1 a day, the least in 5 years-
Operator, other2<1%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I9Fires starting on Network Rail Infrastructure180
M7Door and Door system faults164
Q3NZ Pumps T83
M8Technical failures above the Solebar66
MDTechnical failures below the solebar66
IASignal failure (including no fault found)32
TH(Senior) Conductor/Train Manager31
ZUNo Cause Identified After investigation by both Parties26
TGDriver23
XBVandalism or theft (including the placing of objects on the line)22
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)1,422
MDTechnical failures below the solebar1,388
TH(Senior) Conductor/Train Manager1,142
ICTrack circuit failure (including no fault found)1,107
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,001
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure937
ZUNo Cause Identified After investigation by both Parties744
IASignal failure (including no fault found)700
J3Axle Counter Failure443
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure437