Leaves on the Line

Rotherham Central

RMC North & East route
CSV JSON

1,706 delay minutes

The biggest share (22%) of the delay picked up at Rotherham Central in the four weeks to 9 December 2023 came from how the network was run.

90% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1509%8% 5 a day, more than 3 of the other 4 years-
Signals, points and power1499%16% 5 a day, more than 1 of the other 4 years-
Weather and structures875%7% 3 a day, more than 2 of the other 4 years-
Autumn1056%7% 4 a day, more than 3 of the other 4 years-
External1187%4% 4 a day, the most in 5 years1
Network management36922%17% 13 a day, more than 2 of the other 4 years-
The operators' causes
Train faults29017%16% 10 a day, more than 2 of the other 4 years-
Traincrew19411%11% 7 a day, more than 3 of the other 4 years-
Stations674%3% 2 a day, more than 2 of the other 4 years-
Operations724%5% 3 a day, more than 2 of the other 4 years-
Operator, other1056%7% 4 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver133
OUDelays not Investigated by Network Rail116
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.80
MDTechnical failures below the solebar68
M8Technical failures above the Solebar59
TH(Senior) Conductor/Train Manager55
XPBRIDGE HIT55
QJSpecial working for leaf-fall track circuit operation52
IRBroken/cracked/twisted/buckled/flawed rail50
MNBrake and brake systems faults; including wheel flats where no other cause had been identified49
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver4,669
MDTechnical failures below the solebar4,194
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,489
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,417
IBPoints failure (including no fault found)2,190
M8Technical failures above the Solebar2,149
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps1,886
TH(Senior) Conductor/Train Manager1,804
MNBrake and brake systems faults; including wheel flats where no other cause had been identified1,799
ICTrack circuit failure (including no fault found)1,784