Leaves on the Line

Richmond NLL

RMD Wessex route
CSV JSON

362 delay minutes

The biggest share (42%) of the delay picked up at Richmond NLL in the four weeks to 9 December 2023 came from how the network was run.

73% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track123%8% 0 a day, more than 2 of the other 4 years-
Signals, points and power6819%16% 2 a day, more than 2 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn113%7% 0 a day, more than 2 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management15342%17% 5 a day, more than 2 of the other 4 years-
The operators' causes
Train faults3810%16% 1 a day, more than 1 of the other 4 years-
Traincrew195%11% 1 a day, the least in 5 years1
Stations4713%3% 2 a day, more than 3 of the other 4 years-
Operations3<1%5% 0 a day, more than 2 of the other 4 years-
Operator, other123%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)53
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)41
OCSignaller including mis-routing (not ERTM /ETCS related)34
I4OHLE/third rail power supply failure or reduction30
T2Delay at unstaffed station to non-DOO train24
MNBrake and brake systems faults; including wheel flats where no other cause had been identified20
R8Delay at Station believed to be operator cause and information required from operator (Ops Responsibility)17
IJAWS/ATP/TPWS/Train stop/On track equipment failure15
I6Delays as a result of line blocks / track patrols (including late handback)14
TGDriver13
Since 2018
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,725
TGDriver1,345
VHPassenger Communication cord, door egress or emergency train alarm operated1,236
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,230
M7Door and Door system faults1,136
OCSignaller including mis-routing (not ERTM /ETCS related)1,006
ICTrack circuit failure (including no fault found)911
MDTechnical failures below the solebar826
XDLevel Crossing Incidents including misuse and emergency services being prioritised over rail services795
TH(Senior) Conductor/Train Manager787