Romiley
930 delay minutes
The biggest share (31%) of the delay picked up at Romiley in the four weeks to 9 December 2023 came from autumn leaves.
41% of these minutes were knock-on from something that happened elsewhere first. 77% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 82 | 9% | 8% | 3 a day, the most in 5 years | - |
| Signals, points and power | 46 | 5% | 16% | 2 a day, more than 1 of the other 4 years | - |
| Weather and structures | 8 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| Autumn | 290 | 31% | 7% | 10 a day, the most in 5 years | - |
| External | 29 | 3% | 4% | 1 a day, the most in 5 years | - |
| Network management | 175 | 19% | 17% | 6 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 54 | 6% | 16% | 2 a day, the least in 5 years | - |
| Traincrew | 52 | 6% | 11% | 2 a day, the least in 5 years | - |
| Stations | 10 | 1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 20 | 2% | 5% | 1 a day, the least in 5 years | - |
| Operator, other | 166 | 18% | 7% | 6 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 160 |
| Q3 | NZ Pumps T | 78 |
| TT | Leaf fall Neutral | 76 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 75 |
| OU | Delays not Investigated by Network Rail | 72 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 61 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 35 |
| QH | Adhesion problems due to leaf contamination | 33 |
| TG | Driver | 31 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 29 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 1,417 |
| TG | Driver | 1,354 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 1,326 |
| MD | Technical failures below the solebar | 1,292 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 1,247 |
| TT | Leaf fall Neutral | 1,087 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 1,044 |
| IC | Track circuit failure (including no fault found) | 963 |
| TH | (Senior) Conductor/Train Manager | 886 |
| M7 | Door and Door system faults | 833 |