Leaves on the Line

St Annes-on-the-Sea

SAS North West route
CSV JSON

21 delay minutes

Most of the delay picked up at St Annes-on-the-Sea in the four weeks to 9 December 2023 came from how the network was run.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power419%16%1
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management1257%17%1
The operators' causes
Train faults--16%1
Traincrew524%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OUDelays not Investigated by Network Rail12
TGDriver5
IHPower Supply And Distribution System Failure4
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver253
Q3NZ Pumps T99
TZOther Passenger Train Operating Company causes84
TATrain-crew/loco/stock/unit diagram issues81
M7Door and Door system faults79
TTLeaf fall Neutral67
TRTrain Operating Company Directive59
MDTechnical failures below the solebar59
IBPoints failure (including no fault found)58
MNBrake and brake systems faults; including wheel flats where no other cause had been identified46