Scunthorpe
96 delay minutes
Most of the delay picked up at Scunthorpe in the four weeks to 9 December 2023 came from signal, points and power faults.
4% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 51 | 53% | 16% | 2 a day, more than 2 of the other 4 years | 1 |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 6 | 6% | 7% | 0 a day, the most in 5 years | - |
| External | 3 | 3% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 3 | 3% | 17% | 0 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 17 | 18% | 16% | 1 a day, more than 3 of the other 4 years | 2 |
| Traincrew | 10 | 10% | 11% | 0 a day, more than 1 of the other 4 years | 2 |
| Stations | 3 | 3% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 2 | 2% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 1 | 1% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IE | Signalling Functional Power Supply Failure | 47 |
| M7 | Door and Door system faults | 17 |
| TH | (Senior) Conductor/Train Manager | 10 |
| QI | Cautioning due to railhead leaf contamination | 5 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 4 |
| OU | Delays not Investigated by Network Rail | 3 |
| RQ | Un-booked assistance for a person with reduced mobility joining/alighting, | 3 |
| XQ | Swing bridge open for river or canal traffic | 3 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 2 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 1 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 1,939 |
| M7 | Door and Door system faults | 978 |
| TH | (Senior) Conductor/Train Manager | 514 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 507 |
| IC | Track circuit failure (including no fault found) | 485 |
| MC | Diesel Loco failure, defect, attention | 469 |
| IB | Points failure (including no fault found) | 460 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 452 |
| FW | Late start/yard overtime not explained by Operator | 422 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 420 |