St Erth
283 delay minutes
The biggest share (34%) of the delay picked up at St Erth in the four weeks to 9 December 2023 came from signal, points and power faults.
50% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 36 | 13% | 8% | 1 a day, the most in 5 years | - |
| Signals, points and power | 96 | 34% | 16% | 3 a day, more than 1 of the other 4 years | 2 |
| Weather and structures | 17 | 6% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | 5 | 2% | 7% | 0 a day, the least in 5 years | - |
| External | 3 | 1% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 35 | 12% | 17% | 1 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 54 | 19% | 16% | 2 a day, more than 2 of the other 4 years | 6 |
| Traincrew | 10 | 4% | 11% | 0 a day, the least in 5 years | 8 |
| Stations | 16 | 6% | 3% | 1 a day, the most in 5 years | - |
| Operations | 6 | 2% | 5% | 0 a day, more than 3 of the other 4 years | 2 |
| Operator, other | 5 | 2% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IC | Track circuit failure (including no fault found) | 73 |
| OU | Delays not Investigated by Network Rail | 24 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 22 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 16 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 16 |
| M7 | Door and Door system faults | 13 |
| TG | Driver | 10 |
| MU | Depot operating problem | 9 |
| IA | Signal failure (including no fault found) | 8 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 1,231 |
| TG | Driver | 1,068 |
| IC | Track circuit failure (including no fault found) | 1,045 |
| M7 | Door and Door system faults | 898 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 859 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 761 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 688 |
| IA | Signal failure (including no fault found) | 664 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 605 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 449 |