Shotton
827 delay minutes
The biggest share (32%) of the delay picked up at Shotton in the four weeks to 9 December 2023 came from how the network was run.
47% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 87 | 11% | 16% | 3 a day, more than 2 of the other 4 years | - |
| Weather and structures | 3 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| Autumn | 72 | 9% | 7% | 3 a day, the most in 5 years | - |
| External | 10 | 1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 267 | 32% | 17% | 10 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 185 | 22% | 16% | 7 a day, the most in 5 years | - |
| Traincrew | 129 | 16% | 11% | 5 a day, the most in 5 years | - |
| Stations | 25 | 3% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 31 | 4% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 19 | 2% | 7% | 1 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 156 |
| TG | Driver | 121 |
| QI | Cautioning due to railhead leaf contamination | 59 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 58 |
| MY | Coupler, Coupler system and Jumper cable faults | 35 |
| M8 | Technical failures above the Solebar | 30 |
| OU | Delays not Investigated by Network Rail | 26 |
| TZ | Other Passenger Train Operating Company causes | 26 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 25 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 25 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,239 |
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 1,579 |
| TG | Driver | 1,354 |
| T2 | Delay at unstaffed station to non-DOO train | 1,232 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,159 |
| M8 | Technical failures above the Solebar | 943 |
| IK | Telecom equipment failure (including no fault found) | 769 |
| OU | Delays not Investigated by Network Rail | 652 |
| TH | (Senior) Conductor/Train Manager | 640 |
| TZ | Other Passenger Train Operating Company causes | 608 |