3 delay minutes

Most of the delay picked up at St James Park (Devon) in the four weeks to 9 December 2023 came from how the network was run.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management3100%17%-
The operators' causes
Train faults--16%1
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties3
Since 2018
CodeWhat Network Rail loggedMinutes
M7Door and Door system faults173
IBPoints failure (including no fault found)112
TGDriver87
MDTechnical failures below the solebar69
ZUNo Cause Identified After investigation by both Parties63
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.56
ICTrack circuit failure (including no fault found)52
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail43
OCSignaller including mis-routing (not ERTM /ETCS related)42
VWSevere weather affecting passenger Fleet equipment including follwogin company standards/policies or Rule book instructions42