5,179 delay minutes
The biggest share (18%) of the delay picked up at Salford Crescent in the four weeks to 9 December 2023 came from faulty trains.
84% of these minutes were knock-on from something that happened elsewhere first. 81% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 206 | 4% | 8% | 7 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 568 | 11% | 16% | 20 a day, more than 2 of the other 4 years | - |
| Weather and structures | 429 | 8% | 7% | 15 a day, the most in 5 years | - |
| Autumn | 586 | 11% | 7% | 21 a day, more than 3 of the other 4 years | - |
| External | 239 | 5% | 4% | 9 a day, the most in 5 years | - |
| Network management | 591 | 11% | 17% | 21 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 947 | 18% | 16% | 34 a day, more than 3 of the other 4 years | 1 |
| Traincrew | 579 | 11% | 11% | 21 a day, more than 3 of the other 4 years | - |
| Stations | 260 | 5% | 3% | 9 a day, more than 3 of the other 4 years | - |
| Operations | 307 | 6% | 5% | 11 a day, more than 2 of the other 4 years | - |
| Operator, other | 469 | 9% | 7% | 17 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 392 |
| TT | Leaf fall Neutral | 340 |
| TG | Driver | 308 |
| MD | Technical failures below the solebar | 233 |
| TH | (Senior) Conductor/Train Manager | 231 |
| IB | Points failure (including no fault found) | 212 |
| OU | Delays not Investigated by Network Rail | 175 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 166 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 140 |
| QJ | Special working for leaf-fall track circuit operation | 135 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 18,569 |
| MD | Technical failures below the solebar | 14,268 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 8,384 |
| M7 | Door and Door system faults | 6,384 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 6,352 |
| M8 | Technical failures above the Solebar | 6,019 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 5,651 |
| TH | (Senior) Conductor/Train Manager | 5,492 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 4,746 |
| IB | Points failure (including no fault found) | 4,634 |