Sleaford
1,482 delay minutes
The biggest share (40%) of the delay picked up at Sleaford in the four weeks to 9 December 2023 came from signal, points and power faults.
35% of these minutes were knock-on from something that happened elsewhere first. 67% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 24 | 2% | 8% | 1 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 590 | 40% | 16% | 21 a day, the most in 5 years | - |
| Weather and structures | 98 | 7% | 7% | 4 a day, the most in 5 years | - |
| Autumn | 269 | 18% | 7% | 10 a day, the most in 5 years | 1 |
| External | 25 | 2% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 237 | 16% | 17% | 8 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 64 | 4% | 16% | 2 a day, the least in 5 years | 1 |
| Traincrew | 42 | 3% | 11% | 1 a day, more than 3 of the other 4 years | - |
| Stations | 44 | 3% | 3% | 2 a day, the most in 5 years | - |
| Operations | 18 | 1% | 5% | 1 a day, more than 2 of the other 4 years | 1 |
| Operator, other | 72 | 5% | 7% | 3 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| II | Signalling lineside cable fault | 225 |
| IE | Signalling Functional Power Supply Failure | 152 |
| QH | Adhesion problems due to leaf contamination | 130 |
| QJ | Special working for leaf-fall track circuit operation | 100 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 89 |
| IC | Track circuit failure (including no fault found) | 76 |
| OU | Delays not Investigated by Network Rail | 45 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 44 |
| Q3 | NZ Pumps T | 39 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 35 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 2,257 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,141 |
| TG | Driver | 1,750 |
| J3 | Axle Counter Failure | 1,575 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,558 |
| M8 | Technical failures above the Solebar | 1,456 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,257 |
| IB | Points failure (including no fault found) | 1,246 |
| II | Signalling lineside cable fault | 1,182 |
| IC | Track circuit failure (including no fault found) | 1,129 |