1,482 delay minutes

The biggest share (40%) of the delay picked up at Sleaford in the four weeks to 9 December 2023 came from signal, points and power faults.

35% of these minutes were knock-on from something that happened elsewhere first. 67% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track242%8% 1 a day, more than 1 of the other 4 years-
Signals, points and power59040%16% 21 a day, the most in 5 years-
Weather and structures987%7% 4 a day, the most in 5 years-
Autumn26918%7% 10 a day, the most in 5 years1
External252%4% 1 a day, more than 2 of the other 4 years-
Network management23716%17% 8 a day, more than 3 of the other 4 years-
The operators' causes
Train faults644%16% 2 a day, the least in 5 years1
Traincrew423%11% 1 a day, more than 3 of the other 4 years-
Stations443%3% 2 a day, the most in 5 years-
Operations181%5% 1 a day, more than 2 of the other 4 years1
Operator, other725%7% 3 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IISignalling lineside cable fault225
IESignalling Functional Power Supply Failure152
QHAdhesion problems due to leaf contamination130
QJSpecial working for leaf-fall track circuit operation100
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail89
ICTrack circuit failure (including no fault found)76
OUDelays not Investigated by Network Rail45
OCSignaller including mis-routing (not ERTM /ETCS related)44
Q3NZ Pumps T39
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles35
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar2,257
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,141
TGDriver1,750
J3Axle Counter Failure1,575
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,558
M8Technical failures above the Solebar1,456
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles1,257
IBPoints failure (including no fault found)1,246
IISignalling lineside cable fault1,182
ICTrack circuit failure (including no fault found)1,129