Stone
847 delay minutes
The biggest share (30%) of the delay picked up at Stone in the four weeks to 9 December 2023 came from faulty trains.
81% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 21 | 2% | 8% | 1 a day, the least in 5 years | - |
| Signals, points and power | 133 | 16% | 16% | 5 a day, more than 2 of the other 4 years | - |
| Weather and structures | 12 | 1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| Autumn | 33 | 4% | 7% | 1 a day, the most in 5 years | - |
| External | 16 | 2% | 4% | 1 a day, the least in 5 years | - |
| Network management | 220 | 26% | 17% | 8 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 255 | 30% | 16% | 9 a day, more than 3 of the other 4 years | - |
| Traincrew | 62 | 7% | 11% | 2 a day, more than 2 of the other 4 years | - |
| Stations | 31 | 4% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 11 | 1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 55 | 6% | 7% | 2 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 74 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 71 |
| MD | Technical failures below the solebar | 65 |
| TG | Driver | 47 |
| IH | Power Supply And Distribution System Failure | 33 |
| IB | Points failure (including no fault found) | 30 |
| Q1 | Takeback Pumps | 27 |
| DD | Technical Fleet Holding Code | 25 |
| M9 | Reported fleet equipment defect - no fault found | 22 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 20 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 2,973 |
| I1 | Overhead line/third rail defect | 2,150 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,867 |
| TG | Driver | 1,863 |
| XP | BRIDGE HIT | 1,662 |
| M8 | Technical failures above the Solebar | 1,504 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,431 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,403 |
| MD | Technical failures below the solebar | 1,347 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,220 |