Leaves on the Line

Stone

SNE West Coast South route
CSV JSON

847 delay minutes

The biggest share (30%) of the delay picked up at Stone in the four weeks to 9 December 2023 came from faulty trains.

81% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track212%8% 1 a day, the least in 5 years-
Signals, points and power13316%16% 5 a day, more than 2 of the other 4 years-
Weather and structures121%7% 0 a day, more than 1 of the other 4 years-
Autumn334%7% 1 a day, the most in 5 years-
External162%4% 1 a day, the least in 5 years-
Network management22026%17% 8 a day, the most in 5 years-
The operators' causes
Train faults25530%16% 9 a day, more than 3 of the other 4 years-
Traincrew627%11% 2 a day, more than 2 of the other 4 years-
Stations314%3% 1 a day, more than 1 of the other 4 years-
Operations111%5% 0 a day, the least in 5 years-
Operator, other556%7% 2 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)74
MNBrake and brake systems faults; including wheel flats where no other cause had been identified71
MDTechnical failures below the solebar65
TGDriver47
IHPower Supply And Distribution System Failure33
IBPoints failure (including no fault found)30
Q1Takeback Pumps27
DDTechnical Fleet Holding Code25
M9Reported fleet equipment defect - no fault found22
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)20
Since 2018
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)2,973
I1Overhead line/third rail defect2,150
IRBroken/cracked/twisted/buckled/flawed rail1,867
TGDriver1,863
XPBRIDGE HIT1,662
M8Technical failures above the Solebar1,504
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,431
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles1,403
MDTechnical failures below the solebar1,347
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,220