Swanwick

SNW Wessex route
CSV JSON

0 delay minutes

No delay was picked up at Swanwick in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)45
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)11
ICTrack circuit failure (including no fault found)10
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.10
MDTechnical failures below the solebar6
M9Reported fleet equipment defect - no fault found5
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure5