Southampton Central
6,342 delay minutes
The biggest share (35%) of the delay picked up at Southampton Central in the four weeks to 9 December 2023 came from signal, points and power faults.
77% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 475 | 7% | 8% | 17 a day, the most in 5 years | 8 |
| Signals, points and power | 2,223 | 35% | 16% | 79 a day, the most in 5 years | 25 |
| Weather and structures | 197 | 3% | 7% | 7 a day, more than 3 of the other 4 years | 8 |
| Autumn | 202 | 3% | 7% | 7 a day, more than 2 of the other 4 years | - |
| External | 281 | 4% | 4% | 10 a day, more than 2 of the other 4 years | 3 |
| Network management | 848 | 13% | 17% | 30 a day, more than 2 of the other 4 years | 8 |
| The operators' causes | |||||
| Train faults | 994 | 16% | 16% | 35 a day, more than 3 of the other 4 years | 24 |
| Traincrew | 506 | 8% | 11% | 18 a day, more than 3 of the other 4 years | 32 |
| Stations | 230 | 4% | 3% | 8 a day, the most in 5 years | - |
| Operations | 207 | 3% | 5% | 7 a day, the most in 5 years | 12 |
| Operator, other | 181 | 3% | 7% | 6 a day, more than 1 of the other 4 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IE | Signalling Functional Power Supply Failure | 1,042 |
| IB | Points failure (including no fault found) | 618 |
| MD | Technical failures below the solebar | 502 |
| TG | Driver | 371 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 323 |
| II | Signalling lineside cable fault | 261 |
| I5 | Possession over-run from planned work | 229 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 152 |
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 140 |
| TI | Traincrew rostering problem | 116 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 11,815 |
| TG | Driver | 10,870 |
| IC | Track circuit failure (including no fault found) | 8,159 |
| MD | Technical failures below the solebar | 7,787 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 6,746 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 6,430 |
| IB | Points failure (including no fault found) | 5,708 |
| II | Signalling lineside cable fault | 4,315 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 4,271 |
| TI | Traincrew rostering problem | 4,129 |