400 delay minutes

The biggest share (31%) of the delay picked up at Spalding in the four weeks to 9 December 2023 came from how the network was run.

47% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track4912%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power4712%16% 2 a day, more than 1 of the other 4 years1
Weather and structures154%7% 1 a day, more than 2 of the other 4 years-
Autumn5113%7% 2 a day, the most in 5 years1
External359%4% 1 a day, more than 3 of the other 4 years-
Network management12531%17% 4 a day, more than 3 of the other 4 years-
The operators' causes
Train faults174%16% 1 a day, the least in 5 years1
Traincrew267%11% 1 a day, more than 2 of the other 4 years-
Stations133%3% 0 a day, more than 3 of the other 4 years-
Operations3<1%5% 0 a day, the least in 5 years-
Operator, other195%7% 1 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OUDelays not Investigated by Network Rail63
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.40
QHAdhesion problems due to leaf contamination30
XRCable vandalism or theft25
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles24
QJSpecial working for leaf-fall track circuit operation14
TH(Senior) Conductor/Train Manager14
MDTechnical failures below the solebar13
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail13
FWLate start/yard overtime not explained by Operator11
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,136
J3Axle Counter Failure938
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure919
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles615
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail532
MDTechnical failures below the solebar505
MCDiesel Loco failure, defect, attention424
IASignal failure (including no fault found)308
TGDriver295
IBPoints failure (including no fault found)282