Stockport
4,955 delay minutes
The biggest share (22%) of the delay picked up at Stockport in the four weeks to 9 December 2023 came from signal, points and power faults.
50% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 938 | 19% | 8% | 34 a day, the most in 5 years | - |
| Signals, points and power | 1,113 | 22% | 16% | 40 a day, the most in 5 years | 1 |
| Weather and structures | 772 | 16% | 7% | 28 a day, the most in 5 years | 2 |
| Autumn | 180 | 4% | 7% | 6 a day, more than 2 of the other 4 years | - |
| External | 196 | 4% | 4% | 7 a day, more than 3 of the other 4 years | - |
| Network management | 547 | 11% | 17% | 20 a day, more than 2 of the other 4 years | 3 |
| The operators' causes | |||||
| Train faults | 466 | 9% | 16% | 17 a day, the least in 5 years | 7 |
| Traincrew | 242 | 5% | 11% | 9 a day, more than 1 of the other 4 years | 2 |
| Stations | 123 | 2% | 3% | 4 a day, the least in 5 years | - |
| Operations | 114 | 2% | 5% | 4 a day, more than 2 of the other 4 years | - |
| Operator, other | 265 | 5% | 7% | 9 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IR | Broken/cracked/twisted/buckled/flawed rail | 812 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 509 |
| IB | Points failure (including no fault found) | 405 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 390 |
| JK | Flooding not due to exceptional weather | 369 |
| OU | Delays not Investigated by Network Rail | 184 |
| TG | Driver | 181 |
| XP | BRIDGE HIT | 140 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 127 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 126 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 9,527 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 8,926 |
| IB | Points failure (including no fault found) | 8,774 |
| MD | Technical failures below the solebar | 7,136 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 5,796 |
| M8 | Technical failures above the Solebar | 4,933 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,279 |
| IC | Track circuit failure (including no fault found) | 4,243 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 4,129 |
| M7 | Door and Door system faults | 3,908 |