Shireoaks
82 delay minutes
Most of the delay picked up at Shireoaks in the four weeks to 9 December 2023 came from faulty trains.
33% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 3 | 4% | 16% | - |
| Weather and structures | 4 | 5% | 7% | - |
| Autumn | 16 | 19% | 7% | - |
| External | - | - | 4% | - |
| Network management | 4 | 5% | 17% | - |
| The operators' causes | ||||
| Train faults | 43 | 52% | 16% | - |
| Traincrew | 3 | 4% | 11% | - |
| Stations | - | - | 3% | - |
| Operations | 7 | 9% | 5% | - |
| Operator, other | 3 | 3% | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 43 |
| QI | Cautioning due to railhead leaf contamination | 13 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 4 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 4 |
| T8 | Delays at Station believed to be operator cause and Information required from operator (Ops responsibility) | 4 |
| II | Signalling lineside cable fault | 3 |
| TH | (Senior) Conductor/Train Manager | 3 |
| TZ | Other Passenger Train Operating Company causes | 3 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 3 |
| Q3 | NZ Pumps T | 3 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IK | Telecom equipment failure (including no fault found) | 159 |
| MD | Technical failures below the solebar | 126 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 100 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 89 |
| IC | Track circuit failure (including no fault found) | 84 |
| TG | Driver | 77 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 75 |
| II | Signalling lineside cable fault | 70 |
| IB | Points failure (including no fault found) | 49 |
| Q3 | NZ Pumps T | 49 |