0 delay minutes

No delay was picked up at Stansted Mountfitchet in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect121
XTSevere snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy)39
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)24
IHPower Supply And Distribution System Failure22
ICTrack circuit failure (including no fault found)20
XOExternal trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism)19
IBPoints failure (including no fault found)17
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.14
MNBrake and brake systems faults; including wheel flats where no other cause had been identified12
ITRough ride or bumps reported - cause not known or no fault found9