South Tottenham
396 delay minutes
The biggest share (18%) of the delay picked up at South Tottenham in the four weeks to 9 December 2023 came from traincrew problems.
59% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 5 | 1% | 8% | 0 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 43 | 11% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 13 | 3% | 7% | 0 a day, more than 3 of the other 4 years | - |
| External | 28 | 7% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 58 | 15% | 17% | 2 a day, more than 3 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 58 | 15% | 16% | 2 a day, more than 1 of the other 4 years | - |
| Traincrew | 72 | 18% | 11% | 3 a day, more than 1 of the other 4 years | - |
| Stations | 35 | 9% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 54 | 14% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 31 | 8% | 7% | 1 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 52 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 46 |
| MD | Technical failures below the solebar | 42 |
| RB | Passengers joining/alighting | 35 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 18 |
| I9 | Fires starting on Network Rail Infrastructure | 14 |
| IB | Points failure (including no fault found) | 13 |
| FC | Freight Train Driver error, SPAD, Wrong routing or Missed AWS/DSD [No change] | 12 |
| IA | Signal failure (including no fault found) | 11 |
| I1 | Overhead line/third rail defect | 10 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 9,577 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 6,115 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 4,755 |
| TG | Driver | 4,618 |
| RB | Passengers joining/alighting | 4,013 |
| IQ | Trackside sign blown down, fallen over, missing, defective, mis-placed | 2,061 |
| MD | Technical failures below the solebar | 1,576 |
| M8 | Technical failures above the Solebar | 1,266 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 1,203 |
| IB | Points failure (including no fault found) | 978 |