Leaves on the Line

Strawberry Hill

STW Wessex route
CSV JSON

253 delay minutes

The biggest share (27%) of the delay picked up at Strawberry Hill in the four weeks to 9 December 2023 came from how the network was run.

93% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track187%8% 1 a day, more than 3 of the other 4 years-
Signals, points and power4016%16% 1 a day, more than 3 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn249%7% 1 a day, more than 3 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management6927%17% 2 a day, more than 3 of the other 4 years1
The operators' causes
Train faults4819%16% 2 a day, the most in 5 years3
Traincrew104%11% 0 a day, the least in 5 years1
Stations146%3% 1 a day, more than 3 of the other 4 years-
Operations52%5% 0 a day, more than 2 of the other 4 years-
Operator, other2610%7% 1 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)28
I4OHLE/third rail power supply failure or reduction27
I5Possession over-run from planned work20
IRBroken/cracked/twisted/buckled/flawed rail18
MNBrake and brake systems faults; including wheel flats where no other cause had been identified18
Q3NZ Pumps T17
TTLeaf fall Neutral17
T2Delay at unstaffed station to non-DOO train11
M7Door and Door system faults10
MFEngineering non-technical delays associated with Engineering staff who are not based in an Engineering depot e.g. Cleaners10
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver969
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)767
T2Delay at unstaffed station to non-DOO train617
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure548
TH(Senior) Conductor/Train Manager363
ICTrack circuit failure (including no fault found)283
OCSignaller including mis-routing (not ERTM /ETCS related)263
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail256
MDTechnical failures below the solebar245
IBPoints failure (including no fault found)234