Leaves on the Line

Seven Kings

SVK Anglia route
CSV JSON

3 delay minutes

Most of the delay picked up at Seven Kings in the four weeks to 9 December 2023 came from signal, points and power faults.

0% of these minutes were knock-on from something that happened elsewhere first. 0% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power3100%16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect3
Since 2018
CodeWhat Network Rail loggedMinutes
I5Possession over-run from planned work39
IBPoints failure (including no fault found)20
M8Technical failures above the Solebar20
I9Fires starting on Network Rail Infrastructure18
TXDelays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays)17
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail16
MDTechnical failures below the solebar15
M0Confirmed train cab based safety system fault (including GSMR)14
ICTrack circuit failure (including no fault found)12
IHPower Supply And Distribution System Failure12