1,309 delay minutes

Most of the delay picked up at Taffs Well in the four weeks to 9 December 2023 came from how the network was run.

<1% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power4<1%16% 0 a day, more than 2 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn--7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management1,25996%17% 45 a day, the most in 5 years-
The operators' causes
Train faults181%16% 1 a day, more than 1 of the other 4 years-
Traincrew13<1%11% 0 a day, more than 1 of the other 4 years-
Stations6<1%3% 0 a day, the least in 5 years-
Operations9<1%5% 0 a day, more than 2 of the other 4 years-
Operator, other--7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)1,160
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards96
M9Reported fleet equipment defect - no fault found14
TGDriver13
TZOther Passenger Train Operating Company causes9
J3Axle Counter Failure4
MNBrake and brake systems faults; including wheel flats where no other cause had been identified4
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)3
RBPassengers joining/alighting3
RQUn-booked assistance for a person with reduced mobility joining/alighting,3
Since 2018
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)4,381
JHCritical Rail Temperature speeds, (other than buckled rails)1,283
TGDriver611
ICTrack circuit failure (including no fault found)581
OUDelays not Investigated by Network Rail506
JATSR speed restrictions for track work outside of the Timetable Planning Rules503
MDTechnical failures below the solebar456
T2Delay at unstaffed station to non-DOO train446
MNBrake and brake systems faults; including wheel flats where no other cause had been identified405
IASignal failure (including no fault found)348