Leaves on the Line

Taunton

TAU Western route
CSV JSON

1,215 delay minutes

The biggest share (19%) of the delay picked up at Taunton in the four weeks to 9 December 2023 came from weather and structures.

71% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track16614%8% 6 a day, the most in 5 years1
Signals, points and power20717%16% 7 a day, more than 2 of the other 4 years3
Weather and structures23419%7% 8 a day, the most in 5 years16
Autumn867%7% 3 a day, the most in 5 years-
External585%4% 2 a day, more than 3 of the other 4 years-
Network management1099%17% 4 a day, more than 2 of the other 4 years18
The operators' causes
Train faults746%16% 3 a day, the least in 5 years1
Traincrew14212%11% 5 a day, more than 3 of the other 4 years19
Stations484%3% 2 a day, more than 2 of the other 4 years-
Operations151%5% 1 a day, more than 3 of the other 4 years1
Operator, other776%7% 3 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.137
TGDriver121
JKFlooding not due to exceptional weather104
IBPoints failure (including no fault found)99
OUDelays not Investigated by Network Rail77
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure74
Q3NZ Pumps T65
TTLeaf fall Neutral60
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles46
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)41
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar5,581
TGDriver5,131
M8Technical failures above the Solebar2,574
IRBroken/cracked/twisted/buckled/flawed rail2,455
IBPoints failure (including no fault found)2,454
ICTrack circuit failure (including no fault found)2,120
JATSR speed restrictions for track work outside of the Timetable Planning Rules2,018
M7Door and Door system faults1,856
MNBrake and brake systems faults; including wheel flats where no other cause had been identified1,734
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail1,677