Totnes
388 delay minutes
The biggest share (40%) of the delay picked up at Totnes in the four weeks to 9 December 2023 came from signal, points and power faults.
42% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 41 | 11% | 8% | 1 a day, the most in 5 years | - |
| Signals, points and power | 154 | 40% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Weather and structures | 33 | 9% | 7% | 1 a day, more than 2 of the other 4 years | 7 |
| Autumn | 28 | 7% | 7% | 1 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 41 | 11% | 17% | 1 a day, more than 3 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 67 | 17% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Traincrew | 3 | <1% | 11% | 0 a day, the least in 5 years | 2 |
| Stations | 9 | 2% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 3 | <1% | 5% | 0 a day, more than 3 of the other 4 years | - |
| Operator, other | 10 | 2% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IC | Track circuit failure (including no fault found) | 74 |
| MR | Sanders and scrubber faults | 43 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 32 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 28 |
| I1 | Overhead line/third rail defect | 26 |
| I5 | Possession over-run from planned work | 22 |
| IB | Points failure (including no fault found) | 21 |
| QI | Cautioning due to railhead leaf contamination | 18 |
| J3 | Axle Counter Failure | 17 |
| IA | Signal failure (including no fault found) | 16 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IC | Track circuit failure (including no fault found) | 4,550 |
| MD | Technical failures below the solebar | 2,177 |
| J6 | Lightning strike against unprotected assets | 1,744 |
| XP | BRIDGE HIT | 1,052 |
| M8 | Technical failures above the Solebar | 917 |
| TG | Driver | 743 |
| IB | Points failure (including no fault found) | 690 |
| IA | Signal failure (including no fault found) | 667 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 585 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 571 |