Tring
2,392 delay minutes
The biggest share (38%) of the delay picked up at Tring in the four weeks to 9 December 2023 came from signal, points and power faults.
60% of these minutes were knock-on from something that happened elsewhere first. 92% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 59 | 2% | 8% | 2 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 919 | 38% | 16% | 33 a day, the most in 5 years | 12 |
| Weather and structures | 25 | 1% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | 9 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | 6 | <1% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 664 | 28% | 17% | 24 a day, the most in 5 years | 6 |
| The operators' causes | |||||
| Train faults | 351 | 15% | 16% | 13 a day, more than 3 of the other 4 years | 20 |
| Traincrew | 144 | 6% | 11% | 5 a day, more than 1 of the other 4 years | 6 |
| Stations | 23 | <1% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 40 | 2% | 5% | 1 a day, more than 2 of the other 4 years | - |
| Operator, other | 153 | 6% | 7% | 5 a day, more than 1 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 475 |
| II | Signalling lineside cable fault | 362 |
| IH | Power Supply And Distribution System Failure | 174 |
| J3 | Axle Counter Failure | 156 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 113 |
| TG | Driver | 113 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 111 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 105 |
| M8 | Technical failures above the Solebar | 81 |
| MD | Technical failures below the solebar | 72 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 7,831 |
| TG | Driver | 7,021 |
| J3 | Axle Counter Failure | 6,806 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 6,049 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,480 |
| I1 | Overhead line/third rail defect | 3,479 |
| M8 | Technical failures above the Solebar | 3,466 |
| TH | (Senior) Conductor/Train Manager | 2,853 |
| MD | Technical failures below the solebar | 2,686 |
| M7 | Door and Door system faults | 2,685 |