Leaves on the Line

Thetford

TTF Anglia route
CSV JSON

906 delay minutes

The biggest share (48%) of the delay picked up at Thetford in the four weeks to 9 December 2023 came from track faults.

35% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track43948%8% 16 a day, more than 3 of the other 4 years-
Signals, points and power364%16% 1 a day, the least in 5 years-
Weather and structures121%7% 0 a day, more than 2 of the other 4 years-
Autumn617%7% 2 a day, the most in 5 years-
External222%4% 1 a day, the most in 5 years-
Network management13615%17% 5 a day, the most in 5 years-
The operators' causes
Train faults10512%16% 4 a day, more than 3 of the other 4 years-
Traincrew202%11% 1 a day, more than 3 of the other 4 years-
Stations142%3% 1 a day, more than 3 of the other 4 years-
Operations313%5% 1 a day, the most in 5 years-
Operator, other313%7% 1 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IRBroken/cracked/twisted/buckled/flawed rail350
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.89
MDTechnical failures below the solebar53
QJSpecial working for leaf-fall track circuit operation40
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)32
M9Reported fleet equipment defect - no fault found26
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)23
OSLate start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident17
TGDriver15
ZUNo Cause Identified After investigation by both Parties15
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.13,866
JSCondition of Track TSR outside the Timetable Planning Rules3,977
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles3,198
MDTechnical failures below the solebar1,660
IRBroken/cracked/twisted/buckled/flawed rail1,454
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)1,248
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)1,188
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,010
ICTrack circuit failure (including no fault found)984
J3Axle Counter Failure963