Twickenham
1,059 delay minutes
The biggest share (37%) of the delay picked up at Twickenham in the four weeks to 9 December 2023 came from how the network was run.
80% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 22 | 2% | 8% | 1 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 142 | 13% | 16% | 5 a day, more than 1 of the other 4 years | - |
| Weather and structures | 4 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| Autumn | 78 | 7% | 7% | 3 a day, more than 2 of the other 4 years | - |
| External | 13 | 1% | 4% | 0 a day, the least in 5 years | - |
| Network management | 395 | 37% | 17% | 14 a day, more than 2 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 97 | 9% | 16% | 3 a day, more than 1 of the other 4 years | 1 |
| Traincrew | 109 | 10% | 11% | 4 a day, more than 1 of the other 4 years | 1 |
| Stations | 104 | 10% | 3% | 4 a day, more than 3 of the other 4 years | 1 |
| Operations | 17 | 2% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 79 | 7% | 7% | 3 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 126 |
| I4 | OHLE/third rail power supply failure or reduction | 90 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 84 |
| TG | Driver | 81 |
| Q3 | NZ Pumps T | 51 |
| TT | Leaf fall Neutral | 51 |
| M7 | Door and Door system faults | 48 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 47 |
| T2 | Delay at unstaffed station to non-DOO train | 43 |
| I5 | Possession over-run from planned work | 35 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 9,514 |
| IC | Track circuit failure (including no fault found) | 3,384 |
| TG | Driver | 3,058 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 2,301 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,864 |
| TH | (Senior) Conductor/Train Manager | 1,824 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,754 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,652 |
| M7 | Door and Door system faults | 1,643 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,602 |