Leaves on the Line

Uttoxeter

UTT East Midlands route
CSV JSON

0 delay minutes

No delay was picked up at Uttoxeter in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
I8Animal Strike or Incursion within the control of Network Rail123
IBPoints failure (including no fault found)64
OLSignal Box not open during booked hours54
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail30
XBVandalism or theft (including the placing of objects on the line)17
TATrain-crew/loco/stock/unit diagram issues14
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)13
R7Station delays as a result of overcrowding due to planned events (e.g. sports fixtures, concerts)10
M0Confirmed train cab based safety system fault (including GSMR)4
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure4