Windermere
528 delay minutes
The biggest share (18%) of the delay picked up at Windermere in the four weeks to 9 December 2023 came from faulty trains.
91% of these minutes were knock-on from something that happened elsewhere first. 65% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 44 | 8% | 16% | 2 a day, the most in 5 years | - |
| Weather and structures | 64 | 12% | 7% | 2 a day, more than 3 of the other 4 years | 14 |
| Autumn | 29 | 5% | 7% | 1 a day, the most in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | 1 |
| Network management | 34 | 6% | 17% | 1 a day, more than 3 of the other 4 years | 5 |
| The operators' causes | |||||
| Train faults | 94 | 18% | 16% | 3 a day, more than 2 of the other 4 years | 3 |
| Traincrew | 91 | 17% | 11% | 3 a day, more than 3 of the other 4 years | 12 |
| Stations | 60 | 11% | 3% | 2 a day, the most in 5 years | - |
| Operations | 67 | 13% | 5% | 2 a day, more than 3 of the other 4 years | - |
| Operator, other | 46 | 9% | 7% | 2 a day, more than 3 of the other 4 years | 3 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TH | (Senior) Conductor/Train Manager | 76 |
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 61 |
| TZ | Other Passenger Train Operating Company causes | 37 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 31 |
| Q3 | NZ Pumps T | 29 |
| RB | Passengers joining/alighting | 29 |
| Q1 | Takeback Pumps | 24 |
| DD | Technical Fleet Holding Code | 21 |
| RA | Station Buildings and Facilities (incl Platforms) | 19 |
| IB | Points failure (including no fault found) | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 2,117 |
| MD | Technical failures below the solebar | 1,102 |
| TH | (Senior) Conductor/Train Manager | 803 |
| M8 | Technical failures above the Solebar | 532 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 451 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 417 |
| M7 | Door and Door system faults | 414 |
| TZ | Other Passenger Train Operating Company causes | 379 |
| RB | Passengers joining/alighting | 362 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 355 |