West Ealing
1,398 delay minutes
The biggest share (25%) of the delay picked up at West Ealing in the four weeks to 9 December 2023 came from track faults.
88% of these minutes were knock-on from something that happened elsewhere first. 77% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 350 | 25% | 8% | 13 a day, the most in 5 years | 1 |
| Signals, points and power | 160 | 11% | 16% | 6 a day, more than 3 of the other 4 years | 5 |
| Weather and structures | 18 | 1% | 7% | 1 a day, the most in 5 years | - |
| Autumn | 8 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | 18 | 1% | 4% | 1 a day, more than 3 of the other 4 years | - |
| Network management | 243 | 17% | 17% | 9 a day, the most in 5 years | 5 |
| The operators' causes | |||||
| Train faults | 234 | 17% | 16% | 8 a day, the most in 5 years | 2 |
| Traincrew | 35 | 3% | 11% | 1 a day, more than 1 of the other 4 years | 10 |
| Stations | 3 | <1% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 261 | 19% | 5% | 9 a day, the most in 5 years | 2 |
| Operator, other | 70 | 5% | 7% | 2 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IR | Broken/cracked/twisted/buckled/flawed rail | 245 |
| M2 | Delay due to ATO / ETCS equipment | 169 |
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 140 |
| TZ | Other Passenger Train Operating Company causes | 97 |
| IB | Points failure (including no fault found) | 82 |
| OU | Delays not Investigated by Network Rail | 77 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 51 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 50 |
| TG | Driver | 32 |
| I7 | Engineer's train late into, from or failed in possession | 30 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 1,673 |
| IB | Points failure (including no fault found) | 1,465 |
| IC | Track circuit failure (including no fault found) | 1,190 |
| TG | Driver | 1,023 |
| M2 | Delay due to ATO / ETCS equipment | 859 |
| M7 | Door and Door system faults | 783 |
| J3 | Axle Counter Failure | 740 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 701 |
| I1 | Overhead line/third rail defect | 695 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 687 |