Wigan Wallgate
1,775 delay minutes
The biggest share (18%) of the delay picked up at Wigan Wallgate in the four weeks to 9 December 2023 came from faulty trains.
56% of these minutes were knock-on from something that happened elsewhere first. 89% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 12 | <1% | 8% | 0 a day, more than 3 of the other 4 years | 1 |
| Signals, points and power | 249 | 14% | 16% | 9 a day, more than 3 of the other 4 years | 6 |
| Weather and structures | 106 | 6% | 7% | 4 a day, more than 3 of the other 4 years | 1 |
| Autumn | 247 | 14% | 7% | 9 a day, more than 3 of the other 4 years | - |
| External | 125 | 7% | 4% | 4 a day, the most in 5 years | - |
| Network management | 135 | 8% | 17% | 5 a day, more than 1 of the other 4 years | 175 |
| The operators' causes | |||||
| Train faults | 324 | 18% | 16% | 12 a day, more than 2 of the other 4 years | 22 |
| Traincrew | 245 | 14% | 11% | 9 a day, more than 2 of the other 4 years | 49 |
| Stations | 41 | 2% | 3% | 1 a day, more than 2 of the other 4 years | - |
| Operations | 75 | 4% | 5% | 3 a day, more than 1 of the other 4 years | 1 |
| Operator, other | 217 | 12% | 7% | 8 a day, more than 3 of the other 4 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 198 |
| TT | Leaf fall Neutral | 190 |
| TG | Driver | 150 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 117 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 99 |
| TH | (Senior) Conductor/Train Manager | 95 |
| IB | Points failure (including no fault found) | 73 |
| JT | Points failure caused by snow or frost where heaters are not fitted | 71 |
| M8 | Technical failures above the Solebar | 71 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 56 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 9,978 |
| MD | Technical failures below the solebar | 5,453 |
| TH | (Senior) Conductor/Train Manager | 2,777 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 2,461 |
| M7 | Door and Door system faults | 2,221 |
| Q3 | NZ Pumps T | 1,807 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,801 |
| TZ | Other Passenger Train Operating Company causes | 1,534 |
| TR | Train Operating Company Directive | 1,432 |
| M8 | Technical failures above the Solebar | 1,387 |