Leaves on the Line

Workington

WKG North West route
CSV JSON

1,036 delay minutes

Most of the delay picked up at Workington in the four weeks to 9 December 2023 came from how the network was run.

23% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power19219%16% 7 a day, the most in 5 years-
Weather and structures707%7% 3 a day, more than 2 of the other 4 years2
Autumn4<1%7% 0 a day, more than 2 of the other 4 years-
External6<1%4% 0 a day, more than 1 of the other 4 years-
Network management60658%17% 22 a day, the most in 5 years18
The operators' causes
Train faults6<1%16% 0 a day, the least in 5 years2
Traincrew10210%11% 4 a day, the most in 5 years16
Stations202%3% 1 a day, more than 2 of the other 4 years-
Operations222%5% 1 a day, more than 1 of the other 4 years-
Operator, other9<1%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)505
IASignal failure (including no fault found)151
I5Possession over-run from planned work52
TH(Senior) Conductor/Train Manager50
TGDriver48
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed43
ICTrack circuit failure (including no fault found)25
XTSevere snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy)24
OCSignaller including mis-routing (not ERTM /ETCS related)23
R7Station delays as a result of overcrowding due to planned events (e.g. sports fixtures, concerts)17
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)3,392
TGDriver2,094
JKFlooding not due to exceptional weather1,434
IASignal failure (including no fault found)1,189
ICTrack circuit failure (including no fault found)1,063
TH(Senior) Conductor/Train Manager1,027
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure978
MDTechnical failures below the solebar961
MCDiesel Loco failure, defect, attention674
RBPassengers joining/alighting619