Workington
1,036 delay minutes
Most of the delay picked up at Workington in the four weeks to 9 December 2023 came from how the network was run.
23% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 192 | 19% | 16% | 7 a day, the most in 5 years | - |
| Weather and structures | 70 | 7% | 7% | 3 a day, more than 2 of the other 4 years | 2 |
| Autumn | 4 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | 6 | <1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 606 | 58% | 17% | 22 a day, the most in 5 years | 18 |
| The operators' causes | |||||
| Train faults | 6 | <1% | 16% | 0 a day, the least in 5 years | 2 |
| Traincrew | 102 | 10% | 11% | 4 a day, the most in 5 years | 16 |
| Stations | 20 | 2% | 3% | 1 a day, more than 2 of the other 4 years | - |
| Operations | 22 | 2% | 5% | 1 a day, more than 1 of the other 4 years | - |
| Operator, other | 9 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 505 |
| IA | Signal failure (including no fault found) | 151 |
| I5 | Possession over-run from planned work | 52 |
| TH | (Senior) Conductor/Train Manager | 50 |
| TG | Driver | 48 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 43 |
| IC | Track circuit failure (including no fault found) | 25 |
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 24 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 23 |
| R7 | Station delays as a result of overcrowding due to planned events (e.g. sports fixtures, concerts) | 17 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 3,392 |
| TG | Driver | 2,094 |
| JK | Flooding not due to exceptional weather | 1,434 |
| IA | Signal failure (including no fault found) | 1,189 |
| IC | Track circuit failure (including no fault found) | 1,063 |
| TH | (Senior) Conductor/Train Manager | 1,027 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 978 |
| MD | Technical failures below the solebar | 961 |
| MC | Diesel Loco failure, defect, attention | 674 |
| RB | Passengers joining/alighting | 619 |